2024 Construction Projects in the Lake Street Corridor
The Lake Street Council is tracking the various 2024 construction projects in the Lake Street corridor. During this time, we will support impacted businesses through in-person outreach, updates via our email newsletter, advocating to stakeholders for clear and consistent engagement, and marketing to customers.
The map below shows each project title, website with plans, expected timeline, and contact information. If you have questions about a specific project, we encourage you to use the contact information listed.
Get in touch with the Lake Street Council by emailing business@visitlakestreet.com
Project Locations & Timeline
Excludes: Green Line station construction; E Line station construction
Project Summaries
Reconstruction of intersections for ADA compliance, construction of bus shelters, repaving of Lake Street, and restriping for new street design.
To be completed in 4 sections:
Uptown (Knox to Blaisdell): Early April to late August
Midtown (5th Ave to 21st Ave): Late April to mid-October
West of the Lakes (Chowen to Bde Maka Ska Blvd): Mid-summer
35W (Blaisdell to 5th): Late fall - (restriping only)
Impacts:
Temporary closures to travel lanes and street parking on one side of the street at a time.
Temporary closures at certain intersections for underground utility work and/or intersection redesign.
Concrete removals and replacements of curbs at most intersections.
Construction of bus shelters at key transit intersections.
Current Phase: Under construction in Uptown and Midtown
Hotline: 651-356-6995
Contact: Cody Olson, BLine@MetroTransit.org, 612-248-0642
Subscribe to B Line email updates
Complete reconstruction of Hiawatha-Lake intersection and surrounding
Expected Timeline: April 15 to late October
Current Phase: Under construction
Contact: Jesse Johnson, jesse.johnson@state.mn.us, 612-246-5624
Complete reconstruction of Hennepin Avenue (Lake Street to 26th Street)
Expected Timeline: April 1 - December 2024
Current Phase: Under construction
Contact: Adam Hayow, adam.hayow@minneapolismn.gov, 612-673-2172
Weekly Stakeholder Meeting: Every Friday at 10:00 am via Microsoft Teams
Subscribe to Hennepin Ave Reconstruction email updates
Reconstruction of 1st Ave S: Phase 1 (Lake St to 27th St)
Impacts:
Full street closure during reconstruction of 1st Ave from Lake to 27th St, including underground utility work, construction of new sidewalks, curbs, and street surface
Demolition and reconstruction of 1st Ave bridge over Midtown Greenway
Temporary impacts on Lake to 31st St for bike lane construction and restriping
Expected Timeline: May- December 2024
Current Phase: Preparation
Contact: Stephanie Malmberg, stephanie.malmberg@minneapolismn.gov, 612-673-3365
Subscribe to 1st Ave Reconstruction email updates
View map of areas impacted by construction in 2024 and 2025
Creation of woonerf, Midtown Greenway bikeway connection to Hennepin, and green space
Expected Timeline: Fall - Winter 2024
Current Phase: Input & Design
Contact: Colleen O’Dell, codell@minneapolisparks.org, 612-230-6469
Track installation and construction of the new West Lake Street Station
Current Phase: Under construction
Hotline: 612-373-3933
Contact: Kaydee Kirk, kaydee.kirk@metrotransit.org, 612-373-3941